Service Interruptions

Here you will find a current list of ongoing and upcoming service interruptions across the campus.

Service Interruptions & Outages

 

Date Location and Work Area Impact for Campus Community Project Manager
11/17 - 11/28 Cache la Poudre: Tejon -Dale

Colorado Springs Utilities (CSU) will be performing utility work along Cache La Poudre over the next few weeks in preparation for a water main replacement project scheduled for 2027. This phase involves locating and potholing for underground utilities.
There will be no water shutoffs to campus buildings during this phase. However, the work will require temporary lane closures and restrictions on street parking.


Key Details:
Start Date: Pending city permitting, work is expected to begin Monday, November 17, or Tuesday, November 18.
Duration: Through the first week of December, with a goal to complete potholing by Wednesday, November 26.
Work Hours: Typically 9:00 AM–2:00 PM.
Parking Restrictions: No parking signs will be posted at least 72 hours in advance. Restrictions apply Monday–Friday, 7:00 AM–3:00 PM.


Traffic Impacts:
o Next Week (11/17-11-21): Westbound lane of Cache La Poudre from Tejon to Cascade closed; no street parking.
o Week of Thanksgiving (11/24-11/28): Eastbound lane from Cascade to Dale closed; no street parking.

Michael Brubaker

x7115

mbrubaker@coloradocollege.edu

 

Posted 11/17

     

 

Date

Location and Work Area

Impact for building residents

Project Manager

Ongoing - 11/26

Ticknor Hall

Due to recent flooding, the basement and first floor of Ticknor Hall sustained significant damage. Crews are continuing put-back work in the affected areas, and we will provide updates as the situation progresses.

Beginning November 18, crews will begin floor repair preparation. On November 20, High Plains Flooring will start the refinishing process, which is expected to be completed by November 26. During this time, please expect sanding equipment, construction noise, and contractors accessing the first floor. These areas will be inaccessible for the duration of the project.

Please avoid the affected spaces and give crews the room they need to complete their work safely.

Thank you for your cooperation.

Luke Scott

X6678

lscott@coloradocollege.edu

 

 

 

 Updated 11/18

 

Date

Location and Work Area

Impact for building residents

Project Manager

Ongoing

Edith Gaylord Hall

The elevators in Edith Gaylord Hall are red tagged for scheduled regular maintenance. During this time, the elevators are fully functional.

 We appreciate your patience and understanding as we perform this maintenance to ensure the safety and reliability of the elevator.

 If you have any concerns or require assistance during this time, please reach out.

 

Ben Wirt

X6893

bwirt@coloradocollege.edu

 

 

 

Updated 11/21 

 

Date

Location and Work Area

Impact for building residents

Project Manager

Ongoing

Cossitt Hall

The elevator in Cossitt Hall is red tagged for scheduled regular maintenance. During this time, the elevators are fully functional.

 We appreciate your patience and understanding as we perform this maintenance to ensure the safety and reliability of the elevator.

 If you have any concerns or require assistance during this time, please reach out.

 

Ben Wirt

X6893

bwirt@coloradocollege.edu

 

 

 

Updated 11/21 

 

Date

Location and Work Area

Impact for building residents

Project Manager

Ongoing

Worner Center

The elevators in the Worner Center are red tagged for scheduled regular maintenance. During this time, the elevators are fully functional.

 We appreciate your patience and understanding as we perform this maintenance to ensure the safety and reliability of the elevator.

 If you have any concerns or require assistance during this time, please reach out.

 

Ben Wirt

X6893

bwirt@coloradocollege.edu

 

 

 

Updated 11/21 

    

Date

Location and Work Area

Impact for building residents

Project Manager

Ongoing

El Pomar

The elevators in El Pomar are red tagged for scheduled regular maintenance. During this time, the elevators are fully functional.

 We appreciate your patience and understanding as we perform this maintenance to ensure the safety and reliability of the elevator.

 If you have any concerns or require assistance during this time, please reach out.

 

Ben Wirt

X6893

bwirt@coloradocollege.edu

 

 

 

Updated 11/21

 

Date

Location and Work Area

Impact for building residents

Project Manager

Ongoing

Yalich Student Services Center

The elevator in the Yalich Student Services Center is red tagged for scheduled regular maintenance. During this time, the elevators are fully functional.

 We appreciate your patience and understanding as we perform this maintenance to ensure the safety and reliability of the elevator.

 If you have any concerns or require assistance during this time, please reach out.

 

Ben Wirt

X6893

bwirt@coloradocollege.edu

 

 

 

Updated 11/21 

 

Date

Location and Work Area

Impact for building residents

Project Manager

11/24-11/26

Blanca Apartments

JCI will be onsite to perform the required 5-year inspection of the sprinkler systems at Blanca Apartments. Inspectors will be accessing various parts of the building as needed.

 Please expect loud noises, technicians draining sprinkler lines, and possible odors from the sprinkler water during this work.

 Thank you for your understanding.

Luke Scott

X6678

lscott@coloradocollege.edu

 

 

 

Posted 11/18 

 

Date

Location and Work Area

Impact for building residents

Project Manager

11/24-11/26

11/28

918 N Weber

 

1010 N Weber

 

1120 N Weber

 

224/226 Cache la Poudre

Beginning Monday, November 24 at 8:00 a.m., Wells & West will be replacing doors at 918, 1010, and 1120 N. Weber, as well as 224/226 Cache la Poudre. Contractors will be on site Monday–Wednesday from 8:00 a.m.–5:00 p.m., with the possibility of returning on Friday.

 We will be reusing the existing hardware, and no key changes are expected.

 Please anticipate some noise and contractor presence in these areas during this time.

 

Jamal Westry

X7969

jwestry@coloradocollege.edu

 

 

 

Posted 11/19

 

Date

Location and Work Area

Impact for building residents

Project Manager

11/24-11/26

Packard Hall Basement Hallway

Over fall break, Sodexo will be applying a wax finish to the newly installed flooring in the Packard Hall basement hallway. This process requires three full days of scrubbing and waxing, from Monday, November 24th through Wednesday, November 26th.

 During this time, the area will be fully closed. Signage and taped barricades will be placed at all entrances, including stairwells and elevators.

 To ensure the finish cures properly and to protect the new flooring, no foot traffic will be allowed in the space.

 Thank you for your cooperation and understanding.

 

Damon Mitchell

X6134

dammitchell@coloradocollege.edu

 

 

 

Posted 11/19

 

 

Date

Location and Work Area

Impact for building residents

Project Manager

11/25

44 W Cache La Poudre

On Tuesday, November 25, A-1 Concrete Leveling will be raising three sidewalk panels at 44 W. Cache La Poudre to address a tripping hazard.

This work is located on the section of sidewalk between the pool and the south entrance of El Pomar.

 Please use caution in the area.

John Nichols

X6568

jnichols@coloradocollege.edu

 

 

 

Updated 11/20

 

Date

Location and Work Area

Impact for building residents

Project Manager

Ongoing

Palmer Hall

During Fall Break and Winter Break/Half Block, contractors will be completing HVAC upgrades in Palmer Hall.

 Please see the schedule and impacts below.

 November 22 – November 30 (Fall Break)

  • Remove and reinstall the existing basement-level northwest branch controller
  • Install two (2) new branch controllers
  • Disconnect and relocate existing condensing unit W1 from mechanical room 310 to mechanical room 333
  • Set in place four (4) new condensing units

 December 1 – December 17

  • Work in mechanical rooms 310 and 333 connecting condensing units

 No classroom spaces will be impacted before Winter Break and Half Block.

 December 18 – January 18 (Winter Break & Half Block)
Work will continue in the following spaces:

  • Faculty offices in Geology, History and Political Science
  • Labs: 010A, 010B, 010C, 010E
  • Classrooms: 016, 016A, 018, 022C, 216, 230, 232, 232A, 232B, 233B, 233C

 Additional activities include:

  • System pressure testing, troubleshooting, and fault correction
  • Building automation system controls addressing and programming

 Only the classrooms listed above will be affected during Winter Break and Half Block.

 If you have any questions or concerns, please contact Damon Mitchell directly via email or phone.

 Thank you for your patience as this important work is completed.

 

Damon Mitchell

X6134

dammitchell@coloradocollege.edu

 

 

 

Posted 11/21

Report an issue - Last updated: 11/21/2025

Contact Information

Facilities Services

1125 Glen Avenue
Colorado Springs, CO 80905
Phone: (719) 389-6568
Fax: (719) 389-6981

Contact Us

After-hours/Emergency Contact

Campus Safety: (719) 389-6707

Hours of Operation

Monday thru Friday, 8:00 a.m. to 5:00 p.m.