Service Interruptions
Service Interruptions & Outages
| Date | Location and Work Area | Impact for Campus Community | Project Manager |
| 11/17 - 11/28 | Cache la Poudre: Tejon -Dale |
Colorado Springs Utilities (CSU) will be performing utility work along Cache La Poudre over the next few weeks in preparation for a water main replacement project scheduled for 2027. This phase involves locating and potholing for underground utilities.
|
Michael Brubaker x7115 |
|
|
Posted 11/17 |
|
Date |
Location and Work Area |
Impact for building residents |
Project Manager |
|
Ongoing - 11/26 |
Ticknor Hall |
Due to recent flooding, the basement and first floor of Ticknor Hall sustained significant damage. Crews are continuing put-back work in the affected areas, and we will provide updates as the situation progresses. Beginning November 18, crews will begin floor repair preparation. On November 20, High Plains Flooring will start the refinishing process, which is expected to be completed by November 26. During this time, please expect sanding equipment, construction noise, and contractors accessing the first floor. These areas will be inaccessible for the duration of the project. Please avoid the affected spaces and give crews the room they need to complete their work safely. Thank you for your cooperation. |
Luke Scott X6678 |
|
|
|
|
Updated 11/18 |
|
Date |
Location and Work Area |
Impact for building residents |
Project Manager |
|
Ongoing |
Edith Gaylord Hall |
The elevators in Edith Gaylord Hall are red tagged for scheduled regular maintenance. During this time, the elevators are fully functional. We appreciate your patience and understanding as we perform this maintenance to ensure the safety and reliability of the elevator. If you have any concerns or require assistance during this time, please reach out.
|
Ben Wirt X6893 |
|
|
|
|
Updated 11/21 |
|
Date |
Location and Work Area |
Impact for building residents |
Project Manager |
|
Ongoing |
Cossitt Hall |
The elevator in Cossitt Hall is red tagged for scheduled regular maintenance. During this time, the elevators are fully functional. We appreciate your patience and understanding as we perform this maintenance to ensure the safety and reliability of the elevator. If you have any concerns or require assistance during this time, please reach out.
|
Ben Wirt X6893 |
|
|
|
|
Updated 11/21 |
|
Date |
Location and Work Area |
Impact for building residents |
Project Manager |
|
Ongoing |
Worner Center |
The elevators in the Worner Center are red tagged for scheduled regular maintenance. During this time, the elevators are fully functional. We appreciate your patience and understanding as we perform this maintenance to ensure the safety and reliability of the elevator. If you have any concerns or require assistance during this time, please reach out.
|
Ben Wirt X6893 |
|
|
|
|
Updated 11/21 |
|
Date |
Location and Work Area |
Impact for building residents |
Project Manager |
|
Ongoing |
El Pomar |
The elevators in El Pomar are red tagged for scheduled regular maintenance. During this time, the elevators are fully functional. We appreciate your patience and understanding as we perform this maintenance to ensure the safety and reliability of the elevator. If you have any concerns or require assistance during this time, please reach out.
|
Ben Wirt X6893 |
|
|
|
|
Updated 11/21 |
|
Date |
Location and Work Area |
Impact for building residents |
Project Manager |
|
Ongoing |
Yalich Student Services Center |
The elevator in the Yalich Student Services Center is red tagged for scheduled regular maintenance. During this time, the elevators are fully functional. We appreciate your patience and understanding as we perform this maintenance to ensure the safety and reliability of the elevator. If you have any concerns or require assistance during this time, please reach out.
|
Ben Wirt X6893 |
|
|
|
|
Updated 11/21 |
|
Date |
Location and Work Area |
Impact for building residents |
Project Manager |
|
11/24-11/26 |
Blanca Apartments |
JCI will be onsite to perform the required 5-year inspection of the sprinkler systems at Blanca Apartments. Inspectors will be accessing various parts of the building as needed. Please expect loud noises, technicians draining sprinkler lines, and possible odors from the sprinkler water during this work. Thank you for your understanding. |
Luke Scott X6678 |
|
|
|
|
Posted 11/18 |
|
Date |
Location and Work Area |
Impact for building residents |
Project Manager |
|
11/24-11/26 11/28 |
918 N Weber
1010 N Weber
1120 N Weber
224/226 Cache la Poudre |
Beginning Monday, November 24 at 8:00 a.m., Wells & West will be replacing doors at 918, 1010, and 1120 N. Weber, as well as 224/226 Cache la Poudre. Contractors will be on site Monday–Wednesday from 8:00 a.m.–5:00 p.m., with the possibility of returning on Friday. We will be reusing the existing hardware, and no key changes are expected. Please anticipate some noise and contractor presence in these areas during this time.
|
Jamal Westry X7969 |
|
|
|
|
Posted 11/19 |
|
Date |
Location and Work Area |
Impact for building residents |
Project Manager |
|
11/24-11/26 |
Packard Hall Basement Hallway |
Over fall break, Sodexo will be applying a wax finish to the newly installed flooring in the Packard Hall basement hallway. This process requires three full days of scrubbing and waxing, from Monday, November 24th through Wednesday, November 26th. During this time, the area will be fully closed. Signage and taped barricades will be placed at all entrances, including stairwells and elevators. To ensure the finish cures properly and to protect the new flooring, no foot traffic will be allowed in the space. Thank you for your cooperation and understanding.
|
Damon Mitchell X6134 |
|
|
|
|
Posted 11/19 |
|
Date |
Location and Work Area |
Impact for building residents |
Project Manager |
|
11/25 |
44 W Cache La Poudre |
On Tuesday, November 25, A-1 Concrete Leveling will be raising three sidewalk panels at 44 W. Cache La Poudre to address a tripping hazard. This work is located on the section of sidewalk between the pool and the south entrance of El Pomar. Please use caution in the area. |
John Nichols X6568 |
|
|
|
|
Updated 11/20 |
|
Date |
Location and Work Area |
Impact for building residents |
Project Manager |
|
Ongoing |
Palmer Hall |
During Fall Break and Winter Break/Half Block, contractors will be completing HVAC upgrades in Palmer Hall. Please see the schedule and impacts below. November 22 – November 30 (Fall Break)
December 1 – December 17
No classroom spaces will be impacted before Winter Break and Half Block. December 18 – January 18 (Winter Break & Half Block)
Additional activities include:
Only the classrooms listed above will be affected during Winter Break and Half Block. If you have any questions or concerns, please contact Damon Mitchell directly via email or phone. Thank you for your patience as this important work is completed.
|
Damon Mitchell X6134 |
|
|
|
|
Posted 11/21 |